Partial discharge and loss factor measurements can be taken onsite under online conditions, means the generator or motor is in service, or under offline conditions, means the system is disconnected from the power grid.

On- and Offline Tests

After commissioning high voltage generators or motors, it’s recommended that you take the first baseline measurements under different load conditions on-line, or by applying voltage from an external power source off-line. 

The partial discharge (PD) measurement under off-line conditions can be taken from temporarily installed capacitive couplers, whereas with on-line measurements, permanently installed couplers are most likely required. 

Tan delta, or loss factor, measurements are commonly taken under off-line conditions with variable voltage only.

 

With off-line tests, the entire winding is energised with a conventional high voltage test set or with a resonant test set. In case the neutral connection is opened, each of the three phases can be tested individually. Depending on the accessibility, a coupling to the neutral side of the winding or to the line side may be chosen. The range of the 1 nF couplers (the CC25C/V) makes them a good choice. The CC25C/V offers a quadrupole connection and a high-frequency current transformer output, as well as a voltage divider output for synchronisation and voltage measurement. Permanently installed couplers of the CC20B type may be used as well, as they offer a superimposed voltage signal for synchronisation. Other types of couplers, such as cable type couplers, can be used with some restrictions regarding bandwidth and synchronisation.

On-line tests are usually made with line-side couplers permanently installed. With no permanently installed couplers available, a connection of one coupler to the neutral point may be chosen. This on-line neutral connection bypasses the neutral inductor, neutral transformer, or neutral resistor for high frequency signals. The line-side coupling requires three pieces of CC20B or CC14B couplers installed to the terminals of the machine or to the busbar.

 

References

ICMsystem Operation Manual

IEC TS 60034-27
"Off-line partial discharge measurements on the stator winding
insulation of rotating electrical machines"

Typical Packages:

1) Advanced PD measurement system (off- and online)

2) Standard PD test system (offline)

3) Combined PD and TD measurement equipment (offline)