SUBSTATION MAINTENANCE II | (SSMII | #OPN231)
4.5 DAYS | 3.2 CEUs
This course is the next step after Substation I to enhance the skills needed to perform all substation tasks including a focus on common transformer configurations. It offers training on the components of power and distribution type transformers, including common insulating and cooling mediums and explains common transformer configurations.
This course is available in Spanish.
Learning objectives
To receive 3.2 CEUs, participants must attend 4.5 days of class (32 contact hours) and attain a minimum average of 80% (overall grade with consist of 50% lab practice and 50% final exam). Upon completion of the course labs, participants will demonstrate that they are able to:
- Obtain required information from a transformer nameplate
- Perform needed inspections per NETA/MTS
- Demonstrate and interpret results of required tests performed on transformers
- Calculate temperature corrections
- Summarize ASTM requirements for testing and sampling gas and oil transformers
- Outline storage battery maintenance
Venue information
Some of the products you will be using
10 kV Insulation resistance tester

Transformer Turn Ratio tester TTR

MRCT

Lab and classroom attrire
AVO Training Institute is committed to the personal safety of each participant and require long pants and ANSI rated "safety-toe" work shoes for lab activities. Lecture courses may involve a tour of a workshop area and for this reason open-toe shoes and shorts are not considered appropriate attire for the classroom.
Programme / Scope
Day 1* (7 contact hours)
- Introduction (0.5hr)
- Introduction to Safety (2.5hr)
- Lab Safety Rules
- On-the-Job Safety
- General Safety Precautions
- Nameplate Data (4 hrs)
- Transformer Nameplate
- Labs (4hrs)
- Nameplate Data Exercises
Day 2 (7 contact hours)
- Transformer DC Testing (3 hrs)
- DC Testing
- Insulation Resistance
- Principals of arc interruption
- Winding Resistance Testing
- Labs (4hrs)
- Transformer Insulation Resistance
- Transformer Winding Resistance Testing (single coil)
- Dual Coil Winding
Resistance Test (optional) - Core Ground Testing
(optional)
Day 3 (7 contact hours)
- Transformer AC Testing (3 hrs)
- AC Testing
- Power Factor Testing
- Transformer Bushing Test
- Core Excitation Current Testing
- Turns Ratio Testing
- Labs (4hrs)
- Transformer Turns Ratio
Testing - Transformer Power Factor
Testing - Transformer Core Excitation
Testing - Bushing Testing
- Single Phase Turn Ratio
Testing (optional) - CT Multi-Tap Testing
- Transformer Turns Ratio
Day 4 ( 7 contact hours)
- Transformer Oil Testing (2 hrs)
- Insulating Liquids
- Liquid Sampling
- Sampling for Gas-In-Oil
Analysis - Silicone Insulating Fluid
- Dielectric Breakdown Voltage
Test - Color Testing
- Visual Examination
- Neutralization Number Test
- Interfacial Tension Test
- Moisture Content Test
- Liquid Insulating Power Factor
Testing - Labs (optional)
- Liquid Insulating Power Factor
Testing (optional) - Oil Dielectric Testing (optional)
- Liquid Insulating Power Factor
- Transformer Gas Testing (2 hrs)
- Gas Detection
- Oxygen Testing
- Combustible Gas Testing
- Gas Analysis Interpretation
- Storage Battery Maintenance
(3hrs)- Systems and Components
- Applications
- Battery Types
- Battery In-Service Operation
- Effects of Temperature and Duty
Cycle on Battery Life - Battery Safety
- Battery Inspections
Day 5 (Half Day) (4 contact hours)
-
Conclusion
- Review
- Final Test
*Class scheduling times may vary based on discussions and size of class